The key provisions here are those concerning 'Adjustment of Completion Date' (2.23 – 2.26) and 'Loss and Expense' (4.19 – 4.21).
Starting with delay to the Completion Date, the Contractor is entitled (subject to various notice provisions and provisos) to an extension to the Completion Date as a consequence of 'Relevant Events'. Of these, the two that would appear most directly relevant to Covid-19 are:
- 2.26.12 - exercise after the Base Date by the UK Government or any Local or Public Authority of any statutory power that is not occasioned by a default of the Contractor or any Contractor's Person but which directly affects the execution of the Works; and
- 2.26.14 - force majeure.
Dealing with the exercise of statutory powers ground, if the UK Government exercises such a power after the Base Date (a date selected by the parties in the contract), for example, by closing the borders preventing essential deliveries or quarantining an area where the relevant site is located, this would seem to fall within the 'exercise' ground provided for in clause 2.26.12, could not be said to be due to any Contractor-related default and would seem to directly affect the Works.
Turning to 'force majeure', the standard JCT form contains no definition of this particular Relevant Event. Likewise, there is no clear definition under English case law but to constitute 'force majeure' an event would have to be causative of the relevant delay and would probably have to be outside of the will and control of the parties to the contract and not be due to any default on their part. Obvious examples are war, strikes and weather (albeit exceptionally adverse weather and strikes are covered elsewhere in the JCT form) and an epidemic would also seem to potentially fall under this heading.
When assessing whether the 'force majeure' Relevant Event applies it is important to consider whether the event itself has actually delayed performance or simply made it more expensive to perform. The Courts tend to construe force majeure type clauses very narrowly (particularly where, as here, other events that would otherwise constitute force majeure are dealt with elsewhere) and in the latter case it will be difficult to argue that because an event has caused cost increases it will also fall under this heading as a ground for an extension of time.
It is often forgotten that even if an occurrence is a Relevant Event, these grounds are subject to an important proviso contained in clause 2.25.6; namely that the Contractor must "constantly use his best endeavours to prevent delay in the progress of the Works or any Section, howsoever caused, and to prevent the completion of the Works or Section being delayed or further delayed beyond the relevant Completion Date". Whilst there is no clear legal definition under English law of 'best endeavours' it probably requires the Contractor to at least take all commercially reasonable action, incur reasonable expenses, re-programme and divert reasonable resources in order to prevent any delays to completion. What this means in practice will depend on surrounding circumstances but may go as far as a requirement to take all the steps that a prudent and determined person acting in their own interests would take to bring about the desired result even if that means subordinating its own commercial interests. So, by way of an example, if equipment supply for a project is delayed by the exercise by the Government of a statutory power in relation to the Covid-19 outbreak but the Contractor could foresee this prior to the event becoming critical and use an alternative (albeit more expensive) source of supply, then any delay incurred by a failure to do this may fall foul of this requirement and prevent an extension being granted as a consequence.
Turning to Relevant Matters (the grounds for a loss and expense claim), these are more limited in extent than the Relevant Events under JCT. There is no reference to exercise of statutory powers or to force majeure in clause 4.21 of JCT and Relevant Matters are largely concerned with acts or omissions of the parties to the contract. Consequently, even if a delay to completion as a result of Covid-19 or any resultant exercise of statutory powers could be established as a 'Relevant Event' on either of these two grounds, it is unlikely that there would be any similar 'Relevant Matter' or loss and/or expense entitlement based upon a viral incident such as this.
Clause 2.15.2 of the JCT sets out when changes to Statutory Requirements are treated as a "Change" for the purposes of the contract (carrying an entitlement to time and money). This clause talks about "a change in the Statutory Requirements which necessitates an alteration or modification to the Works" being treated as a Change for the purposes of the JCT rather than restrictions on how sites are operated and labour and materials procured. If legislation brought in to deal with Covid-19 issues means that certain materials cannot be procured and the Works have to be modified accordingly, Contractors may look for a Change under clause 2.15.2 as it brings the advantage of potentially triggering a claim for additional costs as well as time. When considering this issue it is important to bear in mind that the drafting of the clause requires the change in Statutory Requirements to necessitate the alteration.
If the Employer instructs the Contractor to close the site, then clause 3.10 of JCT (which deals with instructions to postpone works) may apply. Alternatively, (depending on the circumstances) the instruction could fall within the ambit of clause 3.9 being an instruction for a Change of the type provided for in clause 5.1.2 of JCT (which deals with the imposition by the Employer of obligations or restrictions relating to matters such as access to the site or limitations on working space or working hours). Instructions under either clause 3.9 or clause 3.10 will trigger an entitlement on the part of the Contractor to both time and money and as such an Employer should exercise caution and seek advice before taking any steps of this nature.
The unilateral closure of a site could potentially in some circumstances amount to an act of impediment, prevention or default by the Employer, allowing the Contractor to claim an extension of time and additional costs arising out of any delays caused. The issue of avoiding an act of prevention may be more acute where any works are being undertaken in a building where access is not controlled by the Employer – for example works to a retail unit in a shopping centre or to a floor within a multi-let office building. Clients need to be proactively liaising with landlords to monitor the status of any buildings where works are on-going and which could be the subject to a decision to close at short notice.
Whilst clearly we all hope that the impact of this virus will be short lived, it is worth noting clause 8.11 of JCT, which allows for a right of termination by either party where before practical completion of the Works, the carrying out of the whole or substantially the whole of the uncompleted Works is suspended for the relevant continuous period stated in the Contract Particulars (a lot of contracts use the default period of 2 months) on account of the two delay grounds noted at clauses 2.26.12 and 2.26.14 of JCT. Clause 8.9 of JCT also allows the Contractor a right to terminate where the whole or substantially the whole of the uncompleted Works is suspended for a period in excess of that stated in the Contract Particulars (again the default period in JCT is set at two months) on account of the Employer's impediment, prevention or default (with such termination being treated as a Client default for the purposes of establishing the Contractor's entitlement to payment on termination).