To explain some of the confusing terminology: a "track" refers to when a cluster might get deployed. The Ten Point Plan states the Government will establish CCUS in two industrial clusters by the mid-2020s (Track 1) and aim for four by 2030 (i.e. a further two, Track 2). The Phase 1 Guidance relates to the Track 1 clusters only.
Phase 1
Within each track there are two phases. In Phase 1 the Government will select one or more clusters. A "cluster" is a transport and storage (T&S) network for carbon dioxide plus at least two associated CO2 capture projects. The entity responsible for the T&S network will be the cluster lead and must provide evidence of a formal collaboration agreement between cluster organisations such as a Memorandum of Understanding or a consortium/partnership agreement. The cluster must be in the UK and must be able to demonstrate that it can be operational by 2030 (although clusters will be evaluated on their pace of delivery, with 2030 being a long stop date).
Phase 2
In Phase 2, the Government will receive applications from individual projects (industrial, power or hydrogen) to connect to the clusters that have been selected for Track 1. This means that if a project was part of a cluster that did not get selected during Phase 1, it can still apply in Phase 2 to connect to a successful cluster, if that is feasible. To be eligible, projects must: be in the UK, have access to a carbon transport solution and storage site, be ready to start pre-FEED studies by the end of 2022 and be operational by the end of 2027 (plus other specific criteria for each type of project).