HEAD V THE CULVER HEATING CO LTD [2021] EWHC 1235 (QB)
HEADLINE SUMMARY
The Court refused a claimant's application to recover Part 36 benefits under CPR 36.17(4) as it was "unjust" because the damages awarded bettered the claimant's Part 36 offer only because the claimant had relied at trial on evidence it had served late, without good reason.
COMMENTARY
One of the benefits of a claimant's Part 36 offer is that it can (if the claimant is awarded greater damages than it was willing to accept from the defendant in its offer) be awarded Part 36 benefits. These benefits may entitle a claimant to interest on the claim, indemnity costs and a further monetary sum. The Part 36 scheme is intended to sanction or reward parties, to encourage attempts to settle claims.
In this decision the Court held, further to CPR 36.17(3), that Part 36 benefits should only be refused (where a Part 36 offer has been beaten) where it would be "unjust" for them to be awarded. Of particular interest in this decision is that the factors the Court must consider are not limited to those listed in CPR 36.17(5), but all relevant circumstances, and those may include whether evidence has been adduced late in proceedings.
It remains the case that Part 36 consequences cannot be considered by the Court in a challenge to late evidence being adduced. The Court made clear, however, that the claimant (C) could not rely on the fact no objections were made by the defendant (D) to the evidence being introduced late, so as to deprive D from arguing that it would be unjust to award the benefits now that the impact of the late evidence is better understood. This decision emphasises the need to adduce evidence as early as possible: the costs consequences of Part 36 offers are not guaranteed.
FACTUAL BACKGROUND
This was a personal injury claim (relating to the death of a man who had contracted mesothelioma) in which C was awarded greater damages than they had offered to accept in a Part 36 offer made between the original judgment and subsequent appeal. C sought consequential orders under CPR 36.17(4) for (a) interest on the whole sum awarded, (b) costs on an indemnity basis from the date on which the relevant period expired, (c) interest on those costs and (d) an additional amount.
The Court had to decide whether to refuse such order based on it being "unjust". The main factual circumstance the Court considered was that C had introduced evidence shortly before the trial, without good reason. The evidence proved that the deceased would have reduced his shareholding in a business (as his involvement was set to reduce). This was to C's benefit as there was no investment income for D to offset against lost earning capacity (which there might otherwise have been). This was deemed likely to have caused the damages awarded to be greater than the amount in C's earlier Part 36 offer.
KEY LEGAL POINTS
Despite this finding, Johnson J maintained that it remains a "formidable obstacle" to show that the granting of consequential orders would be unjust (pursuant to Smith v Trafford Housing Trust [2012] EWHC 3320 (Ch)).
The Court must consider the factors listed under CPR 36.17(5) in deciding whether it would be unjust to make the order. But all relevant circumstances are not limited to the factors listed in CPR 36.17. In this case, the introduction of the late evidence affected the quantum of the claim to C's benefit. As the possibility of Part 36 benefits was only available because C relied on evidence served late without good reason, it was deemed unjust to award them. It was not necessary for the Court to establish the precise monetary difference the evidence caused as it was sufficient that C beat their Part 36 offer by a 'relatively small proportion of the overall value of the claim' : any significant increase in the value of the claim was 'likely to have made all the difference'. It was also not necessary for D to have objected to the late evidence when it was initially introduced.
Finally, it is also worth noting that it was not relevant to consider whether making the order might result in D paying more than the amount required to compensate C for the losses sustained. The rationale for this was that such potential outcome is 'inherent in a scheme… of sanctions and rewards' and is intended to encourage early dispute resolution.