Whilst X29 was previously published by NEC as an option in its own right, this has now been incorporated into all the NEC main contract forms. Whilst there are some variations between the different forms, the key points are:
- The Client can set out its Climate Change Requirements in the Scope.
- The Contractor submits a Climate Change Plan showing how the Contractor intends to meet the Climate Change Requirements.
- There is a Climate Change approval process for approval and sign off.
- There is a mechanism allowing the Contractor to propose Scope changes to reduce climate change impacts of the works together with associated risks, quotations and programme changes.