The new building safety regime under the BSA applies to both construction of new HRBs and the refurbishment of existing HRBs.
The new regime is likely to be extremely challenging for industry, in particular, it heralds:
- far more constraint around changes to initial designs, with considerably more up-front information required about design materials
- built-in delays of between 2 and 6 weeks for minor and major changes to design, respectively, whilst regulator approval is awaited
- an inability to apply for a completion certificate until all work, including snagging, is completed
- a further 12 week delay preventing residential occupation of the HRB at the conclusion of the build whilst regulator sign-off is sought (needed to obtain a completion certificate)
Where the new regime applies, dutyholders will need to meet a series of requirements during the construction phase. The current proposals include:
- Relevant functional requirements under applicable building regulations
- Commencement notices;
- Dutyholder and competence regulations;
- Compliance with inspection regime;
- New statutory change control process;
- Regulations related to a new client / Principal Contractor / Principal Designer;
- Mandatory occurrence reporting requirements;
- Golden thread information requirements to manage and store information relevant to the building work;
- Completion certificate applications / Partial completion certificate applications;
- Reviews, appeals and section 30A procedures;
- Enforcement powers applicable to higher-risk building work.