PAPs have the same statutory obligations for assessing and managing building safety risks in their own area of the building as other APs but will also have significant additional responsibilities for meeting specific statutory obligations for the whole building.
Registration
All occupied HRBs will need to be registered with the BSR by the PAP. The application is subject to a fee and made via the BSR’s digital platform. It must identify the APs and include various basic details of the building, including:-
- the PAP's organisation type;
- the details of anyone applying on behalf of the PAP;
- a single point of contact;
- a description of the building including its address, residential unit numbers, height, storeys and the year it was completed; and
- various building certificate details for buildings not constructed under the BSA regime.
The requirement to register comes into force from today, 6 April 2023. If an applicable building is fully completed and occupied before this date the PAP will have a 'reasonable' time to register the building (guidance indicates 1 October 2023). If an applicable building is fully or partially completed after this date, the building cannot be occupied before registration.
Certification
The PAP for a registered higher-risk building must apply for a building assessment certificate within 28 calendar days of receiving a direction from the BSR to do so unless they have a reasonable excuse.
For new builds, the PAP will be directed to apply for a building assessment certificate within 6 months of occupation.